A $26 million infrastructure upgrade program is bringing much needed renovations to the 57 year-old McNally Building, as well as the Burke Building and the Patrick Power Library. The effort is designed to create enhanced graduate and research space and support improvements to facilities for research and development.


Progress Highlights:
- The driveway in front of McNally main is nearly complete. No parking spaces have been lost.

- Registrar’s Front Counter & Student Accounts will remain in BMO Lounge in the Loyola Building.
- The Main lobby will be complete and operational by Sept. 1.
- The washrooms in the Burke Building will be out of service until early October.
- Nine days have been set aside in late August and early September to move faculty offices from McNally South 2nd, 3rd and 4th floors. They will be relocated to Vanier C House and other temporary locations.


Scheduled for August Completion:

- McNally roof
- McNally Main 1st floor corridors
- McNally brickwork
- McNally 3rd floor
- McNally 2nd floor
- All classrooms in McNally East
- Burke skylights, roof
- McNally Main Basement Astronomy & Physics Classroom
- McNally Science Pedway


Scheduled for September Completion:
- All public areas in McNally East (ITSS)
- Burke washrooms closed for renovations
- McNally - Science Pedway


Scheduled for October Completion:
- Library 2nd floor renovations
- McNally East (ITSS) Server Room
- Burke washrooms
- Library elevator upgrade

UPDATES

- For the latest updates

We're building on your expectations....

Atrium Photo

For an update on the

MCNALLY NORTH CAMPUS renovations

For the latest on the THE ATRIUM

or visit - TheAtrium.ca


   

This page last modified Thursday, 24-Mar-2011 15:49:56 ADT